Update: The East Midlands Gateway website has now been updated with information relating to the Kegworth Bypass. On there is a useful map with timeline of works. Please click on the link below to take you to the website.

http://slp-emg.com/community/infrastructure/kegworth-bypass/

We are pleased to announce that work on Kegworth Bypass commenced on 4th September 2017 and is now due for completion by 31 October 2018 several months earlier than previously report.

The works are being undertaken by Buckingham Group Contracting limited, who's contact details are;

Website: www.buckinghamgroup.co.uk
Site email: kegworthbypass@buckinghamgroup.co.uk
General Enquiries: 07980 999780
Considerate Constructors contact: 0800 7831423

Resident Newsletter November 2017

Update: Ashby Road was reopened yesterday by Winvic.